Making Availability and Economics Physical

A cost and reliability model that connects fusion component life, maintenance time, recirculating power, construction, financing, and fleet learning to delivered energy.

Difficulty
Advanced
Evidence
Hypothesis
Readiness
TRL 1 / 9
Review
Author reviewed
Sources
4
Reading time
10 min

Abstract

Fusion economics is often reduced to machine size or projected cost per kilowatt. I instead begin with the physical causes of delivered energy and cash flow. Net electrical output depends on thermal conversion and internal power. Annual generation depends on planned and unplanned availability. Capital cost depends on material quantity, manufacturing complexity, buildings, nuclear systems, construction duration, and financing. Replacement cost depends on neutron life and remote outage design. I develop a transparent model that preserves uncertainty and separates first-of-a-kind demonstration value from mature fleet economics. The most important variables are not isolated plasma gain or field strength. They are net power, component lifetime, replacement duration, construction schedule, and the rate at which factories and operators learn.

Cost begins with delivered megawatt-hours

The levelized cost of electricity is schematically

LCOE=∑t(Ccapital,t+CO&M,t+Cfuel,t+Cdecom,t)/(1+r)t∑tEt/(1+r)t.\mathrm{LCOE}=\frac{\sum_t(C_{\mathrm{capital},t}+C_{\mathrm{O\&M},t}+C_{\mathrm{fuel},t}+C_{\mathrm{decom},t})/(1+r)^t}{\sum_tE_t/(1+r)^t}.

The formula is familiar. The difficult part is defending each term for a plant that does not yet exist. A precise output from uncertain inputs is not reliable knowledge.

I therefore report ranges and sensitivities. Every assumption carries an evidence class: measured in relevant service, measured in a partial environment, extrapolated by validated model, analogous industry data, or design target.

Net power is the denominator before availability

Gross generator rating can conceal large internal loads. I retain

Pnet=ηthPrecoverable−Precirc.P_{\mathrm{net}}=\eta_{\mathrm{th}}P_{\mathrm{recoverable}}-P_{\mathrm{recirc}}.

Current drive, neutral beams, radiofrequency sources, cryogenics, coolant pumps, vacuum, tritium processing, magnets, heat rejection, remote systems, and buildings consume power. Some loads are continuous; others peak during startup or maintenance.

A plant producing 800 MWe800\ \mathrm{MW_e} gross with 300 MWe300\ \mathrm{MW_e} internal load sells 500 MWe500\ \mathrm{MW_e}. A ten-percent reduction in gross power is serious, but a 100 MWe100\ \mathrm{MW_e} rise in recirculating load reduces saleable output by twenty percent. Wall-plug efficiency deserves plant-level prominence.

Availability multiplies every capital dollar

Availability can be written as

A=Tscheduled−Tplanned−TforcedTscheduled.A=\frac{T_{\mathrm{scheduled}}-T_{\mathrm{planned}}-T_{\mathrm{forced}}}{T_{\mathrm{scheduled}}}.

Planned outages replace blankets, divertors, pumps, diagnostics, and other life-limited equipment. Forced outages follow faults. Their durations depend on diagnosis, cooldown, access, spares, remote work, testing, and restart.

For repairable equipment, a simple steady estimate is

A≈MTBFMTBF+MTTR.A\approx\frac{\mathrm{MTBF}}{\mathrm{MTBF}+\mathrm{MTTR}}.

Fusion is not one component, and this equation omits redundancy, common cause, planned life, and resource contention. It still shows that reducing mean time to repair can matter as much as extending mean time between failures.

VariablePhysical evidence neededEconomic effect
Divertor and blanket lifeIntegrated heat and neutron exposurePlanned outage frequency and replacement inventory
Sector exchange durationFull-scale rehearsed remote sequenceOutage length and hot-cell capacity
Heating efficiencyGrid-to-absorbed-power measurementNet output and equipment size
Magnet reliabilityPopulation, joint, and quench evidenceForced outage and major capital risk
Construction scheduleCompleted design, supply, and installation workInterest during construction and revenue delay

Component life creates a size trade

Higher neutron wall loading can produce more power from a smaller surface, but it consumes material life faster. A larger machine may cost more initially while reducing load density and extending replacement intervals.

If allowable lifetime fluence is Fmax⁡F_{\max} and wall loading is qnq_n, full-power life is approximately

tlife=Fmax⁡qn.t_{\mathrm{life}}=\frac{F_{\max}}{q_n}.

Real life also depends on temperature, stress, transmutation, joints, fatigue, and transients. The relation reveals why maximum power density is not automatically minimum cost. Plant systems codes must allow size and maintenance architecture to change together.

Construction time is a technology variable

Large projects incur financing costs before earning revenue. Delay also freezes design, ties up skilled teams, and exposes interfaces to rework. A compact machine with difficult assembly can take longer than a larger modular one.

I separate design completion, licensing, long-lead procurement, civil works, factory production, site assembly, commissioning, and contingency. Schedule logic includes resource limits and rework, not only ideal precedence.

Modular construction can shift work to controlled factories and permit parallelism. It can also multiply transport, alignment, welding, inspection, and configuration interfaces. The economic model credits modularity only after a detailed installation sequence demonstrates its benefit.

First plants and mature plants answer different questions

A first-of-a-kind plant carries engineering, qualification, licensing, supply-chain, tooling, and commissioning costs that later units should not repeat. It may rationally cost more than the energy it produces because its product includes evidence.

Nth-of-a-kind projections use learning curves:

CN=C1Nb,b=ln⁡(1−L)ln⁡2,C_N=C_1N^b, \qquad b=\frac{\ln(1-L)}{\ln2},

where LL is the learning rate per cumulative doubling. Learning is not automatic. It requires design stability, repeated suppliers, feedback, workforce continuity, and enough units. A fleet of unique national projects does not experience the same learning as a production line.

Materials and waste belong in the ledger

Fusion fuel mass is small, but the plant contains steel, concrete, copper, superconductors, tungsten, lithium, beryllium or lead in some blankets, cryogenic equipment, turbines, and power electronics. Replacement sectors create activated material streams.

Low-activation material choices can reduce long-term waste burden, yet manufacturing yield, recycling, clearance rules, decontamination, and disposal routes need real cost. Decommissioning funds and component storage begin with plant operation.

The supply of enriched lithium, tritium, specialty alloys, superconducting tape, high-purity tungsten, large forgings, and qualified electronics may constrain build rate before raw resource quantity does. Factory capacity is an economic state variable.

Value depends on the energy system

Fusion may provide firm electricity, process heat, reserve, ramping, hydrogen, or thermal storage. Revenue should be modeled against the grid it joins rather than an undifferentiated energy price.

A high-capital plant benefits from high utilization, but a future grid with abundant variable generation may value flexible output. Thermal storage can keep the fusion core steady while shifting electricity. The added tanks and exchangers compete with improved market value.

OutputMaximize saleable energy

Close thermal efficiency, internal power, duty, and grid service.

UptimeDesign physical availability

Connect component life, remote work, spares, and recovery distributions.

DeliveryControl capital and schedule

Use completed design, factories, modular interfaces, and reference classes.

LearningReproduce a stable plant family

Convert first-unit evidence into manufacturing and operating improvement.

Figure 1. Four physical systems determine fusion economics.

A decision model should be falsifiable

I maintain a ranked list of value-of-information questions. If divertor life dominates cost uncertainty, material and exhaust testing may be worth more than a small confinement improvement. If construction schedule dominates, a full-scale assembly demonstrator may outrank another conceptual optimization.

AssumeDeclare range and evidence class PropagateCalculate output, cost, and uncertainty TestFund evidence with greatest decision value UpdateRevise design and investment gate
Figure 2. Economics directs research toward assumptions that control the decision.

The model cannot be validated by analysis alone. Construction and commissioning reveal whether tolerances, supply chains, test boundaries, software, procedures, and organizations actually form an operable plant. The next report designs that transition from completed parts to measured net power.

Evidence register

Sources

  1. Fusion Science and Technology RoadmapU.S. Department of Energy
  2. DOE Fusion Energy Strategy 2024U.S. Department of Energy
  3. Extrapolating Costs to Commercial Fusion PowerUK Atomic Energy Authority
  4. DEMOEUROfusion

Unresolved work

Open problems raised here

OpenReliability engineering · Remote maintenance · Operations research

Establish fusion availability evidence

What failure rates, component lives, maintenance durations, common-cause events, and recovery distributions are defensible for a first commercial plant?

Next tractable stepCreate an open evidence register that connects test facilities, component populations, full-scale mockups, and operating campaigns to plant availability assumptions.
OpenCost engineering · Industrial economics · Project delivery

Validate the fusion cost-learning model

Which capital, schedule, supply-chain, financing, and learning assumptions remain credible as fusion moves from first-of-a-kind plants to a repeatable fleet?

Next tractable stepBenchmark a transparent reference-class model against large scientific facilities, cryogenic plants, turbines, nuclear projects, superconducting magnets, and early fusion builds.

Continue the work

Challenge, correct, or extend this report.

Bring evidence, expose a weak assumption, or propose the next experiment. Confirmed work can become a revision to the report.

Authorship and provenance

A named, versioned record.

Author
Mingkai
Rights holder
Mingkai
First published
August 24, 2026
Current revision
v1.0 / 2026-08-24

Suggested citation: Mingkai. “Making Availability and Economics Physical.” Physical Extremes, 2026, https://mingkaibuilds.github.io/Frontiers/reports/fusion-energy/making-availability-and-economics-physical/

© 2026 Mingkai. Physical Extremes™. All rights reserved.